Each week Kempsey Shire Council prepares a report detailing the work that our infrastructure crews have carried out in the week prior and plan to deliver in the coming week.

Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.

LAST UPDATE: Friday 3 May 2024 

Road Construction and Maintenance Program 

Works Achieved This Week Proposed Works Next Week
Regional Roads – Construction, Rehabilitation & Maintenance
Smithtown Road - MVW to 201 Smithtown Road, Seven Oaks - Stage 1 Smithtown Road - MVW to 201 Smithtown Road, Seven Oaks - Stage 1
 Preparation of pavement  
Completed  
 Sealing  
Completed  
Macleay Valley Way / Second Lane Intersection, Kempsey Macleay Valley Way / Second Lane Intersection, Kempsey
Setting up of compound   
Complete  
  Drainage Works 
  To commence
Rural Local Roads – Construction, Rehabilitation & Maintenance
Works currently in planning. To be delivered at a later date.
Urban Local Roads – Construction, Rehabilitation & Maintenance
Works currently in planning. To be delivered at a later date.
Heavy Patching Program
Works currently in planning. To be delivered at a later date.
Sealed Roads – Resealing Program
Works currently in planning. To be delivered at a later date.
Sealed Roads – Maintenance Program
 MVW - Between Kempsey and Frederickton  MVW - Between Kempsey and Frederickton
 Blackout of speed limits  
Complete  
 South West Rocks Area  
Complete  
 Ocean Avenue  
Complete   
 Reserve Road  
Complete  
  Aldavilla Area 
  To commence
  Sherwood Area
  To commence
  Yarravel Area 
  To commence
 Reactive Pothole Maintenance   Reactive Pothole Maintenance
Ongoing Ongoing
Reflect Defects Reflect Defects
Ongoing Ongoing
Sealed Road - Line Marking Program  
Arakoon Road  
Complete  
Bream Close  
Complete  
Marlin Circuit   
Complete  
Armidale Road  
Complete  
Unsealed Gravel Re-sheeting Program

Nagels Falls Road
  To commence 
Unsealed Roads – Maintenance Grading Program
 Maria River Road Maria River Road
Deferred To commence
Mines Road  
Complete  
 Jacks Crossing  
Complete  
Dungay Creek Road Dungay Creek Road
75% complete To complete
Yessabah Road  Yessabah Road
75% complete - Deferred To complete
  Allens Access
  To commence
  Warbro Brook Road
  To commence
Roadside Slashing and Vegetation Control Program
Collombatti Area Colombatti Area
70% complete  To complete
  Plummers Lane 
  To commence
  Macleay Valley Way North 
  To commence 
 Macleay Valley Way South  
Complete  
South Kempsey Area  South Kempsey Area
70% complete To continue

Civil Construction Program

Works Achieved This Week Proposed Works Next Week

Kerb and Gutter Program

 Cochrane Street, West Kempsey Cochrane Street, West Kempsey
Kerb and gutter repairs Kerb and gutter repairs
70% complete Deferred
Capital Works Program
Tozer Street, West Kempsey Tozer Street, West Kempsey
New footpath installation  New footpath installation
40% complete To continue
 New driveway and footpath installation  New driveway and footpath installation
 15% complete - Deferred To continue
 Back filling of kerb and verge remediation  Back filling of kerb and verge remediation
 15% complete   To continue
Buchanan Drive/Gregory Street, South West Rocks Buchanan Drive/Gregory Street, South West Rocks
Footpath Installation Footpath Installation
90% complete To continue
 Kerb and gutter installation  
Complete  
 Installation of traffic islands  Installation of traffic islands 
10% complete To continue 
Footpath Program
Works currently in planning. To be delivered at a later date.
Stormwater Drainage Program
Works currently in planning. To be delivered at a later date.

Traffic Facilities

Works Achieved This Week Proposed Works Next Week
Signs
Collombatti Road, Collombatti Collombatti Road, Collombatti
Signs and pavement markings Signs and pavement markings
50% complete To continue
Tozer Street, West Kempsey Tozer Street, West Kempsey
Signs and pavement markings Signs and pavement markings
Deferred Deferred
Burrawong Drive/Rosedale Avenue, South West Rocks Burrawong Drive/Rosedale Avenue, South West Rocks
Signs and pavement markings Signs and pavement markings
In progress To continue
Macleay Valley Way, Kempsey Macleay Valley Way, Kempsey
 Signs and pavement markings  Signs and pavement markings
 In progress To continue
 Sea Street, West Kempsey Sea Street, West Kempsey
Signs and pavement markings Signs and pavement markings
 In progress To continue
Bloomfield Street, South Kempsey Bloomfield Street, South Kempsey
Curve alignment markers Curve alignment markers
 In progress To continue
 Mitchell Street, South West Rocks  Mitchell Street, South West Rocks
Signs, splitter island and pavement markings Signs, splitter island and pavement markings
 In progress  To continue
Ranch Road, Crescent Head Ranch Road, Crescent Head 
Signs  Signs
In progress To continue
 Belgrave Street, Kempsey Belgrave Street, Kempsey
Signs and pavement markings Signs and pavement markings
 In progress To continue
Sherwood Road, Sherwood  Sherwood Road, Sherwood
 Signs Signs
In progress  To continue
 Pacific Street, Crescent Head Pacific Street, Crescent Head
Signs and pavement markings  Signs and pavement markings 
 In progress To continue
Temagog Road, Temagog Temagog Road, Temagog
Signs Signs
In progress To continue
Belgrave Street, Kempsey Belgrave Street, Kempsey
Killuke Crescent, Crescent Head  Killuke Crescent, Crescent Head
 Signs and pavement markings Signs and pavement markings
In progress To continue
 Sherwood Road, Sherwood Sherwood Road, Sherwood
Signs Signs
In progress To continue
Customer requests/Maintenance Customer requests/Maintenance
Ongoing To continue

Bridge Infrastructure Program

Works Achieved This Week Proposed Works Next Week
Bridge Replacement Program
Buchanans Bridge, Belmore River Left Bank Road, Belmore River Buchanans Bridge, Belmore River Left Bank Road, Belmore River
Installation of guard rail Installation of guard rail
50% complete - deferred Deferred
 Installation of Telstra
Complete  
Installation of watermain   Installation of watermain 
Deferred Deferred
 Loftus Bridge, Belmore River Left Bank Road Loftus Bridge, Belmore River Left Bank Road
Installation of guard rail Installation of guard rail
50% complete - deferred Deferred
 Installation of watermain Installation of watermain 
Deferred Deferred
Thurgoods Bridge, Upper Belmore River Right Bank Thurgoods Bridge, Upper Belmore River Right Bank
Installation of guard rail Installation of guard rail
50% complete - deferred Deferred
 Installation of watermain Installation of watermain  
Deferred Deferred
Warbro Bridge, Brassils Creek Road, Toorooka Warbro Bridge, Brassils Creek Road, Toorooka
Installation of guard rail Installation of guard rail
50% completed - Deferred Deferred
Approaches Approaches
95% complete To complete
Dunbars Nulla Nulla Creek Road, Bellbrook   Dunbars Nulla Nulla Creek Road, Bellbrook
 Demolition of existing bridge Demolition of existing bridge 
10% complete To continue 
O'Neills Bridge, Nulla Nulla Creek Road, Bellbrook O'Neills Bridge, Nulla Nulla Creek Road, Bellbrook
Demolition of existing bridge Demolition of existing bridge 
10% complete To continue 
Timber Bridge Maintenance Program
Works currently in planning. To be delivered at a later date.
Wharves, Jetties and Footbridge Program
Works currently in planning. To be delivered at a later date.
Parks and Facilities Program
Works currently in planning. To be delivered at a later date.

Sporting Infrastructure Program

Works Achieved This Week Proposed Works Next Week
Sporting Infrastructure
Works currently in planning. To be delivered at a later date.
Sports Field Maintenance
Works currently in planning. To be delivered at a later date.
Open Spaces Program

Reserve Road, Grassy Head Playground Replacement

Reserve Road, Grassy Head Playground Replacement
Delivery and installation of playground structure Delivery and installation of playground structure
 Deferred  Deferred
Services Club Park, Belgrave Street, Kempsey Building Renovation  Services Club Park, Belgrave Street, Kempsey Building Renovation
 Installation of new plumbing Installation of new plumbing 
50% complete To continue 
Tiling  Tiling
50% complete To continue 
South Kempsey Park, South Kempsey Pump and Learn to Ride Track  South Kempsey Park, South Kempsey Pump and Learn to Ride Track 
Installation of site fencing   
Complete  
Earthworks  Earthworks 
25% complete To continue

Flood mitigation works

Works Achieved This Week Proposed Works Next Week
Flood Mitigation Maintenance
Works currently in planning. To be delivered at a later date.
Riverbank Rock Protection Program
Works currently in planning. To be delivered at a later date.

 Additional Projects and Other Works

Works Achieved This Week Proposed Works Next Week
 River Street, West Kempsey  
Footpath repairs  
Complete  
River Street, Greenhill  
Footpath repairs  
Complete  
Kemp Street, West Kempsey   
Footpath repairs   
Complete   
Stormwater drainage maintenance Stormwater drainage maintenance
Ongoing Ongoing
Shire Wide - Minor Maintenance Response Shire Wide - Minor Maintenance Response
Customer requests Customer requests
Ongoing Ongoing